Resourcing the Project Plan
Once the tasks have been setup, the project needs to be resourced as to who is doing which task when. (If you need this information).
To be able to use this facility within Microsoft Project.
• The resources need to set up,
• Costs need to be allocated to resources
• Resources need to be allocated to tasks
• Resource over allocation considered
Set up Resources
Resources need to set up on the Resource sheet. Change the view by Menu, View, Resource Sheet.
Here the resource information can be entered for how ever many resources required. The information that needs to be provided is
Name | Enter the resource name |
Initials | Will only pick up the first letter can be altered as required |
Resource type | Select type of Resource it is, Work- works to a calendar, Material – quantities required can be specified. Cost – amounts can be specified eg hotel bills. |
Material Label | If the resource type is Material then a label can be displayed |
Max units | How many of the resource are there |
Std rate: | the standard rate of pay can be proceeded by the appropriate pay period eg /d, /w, /y |
Ovt rate: | the overtime rate of pay - will only come into effect is overtime is specified |
Per Use: | The call out charge - will be charged for every occurrence of usage of this resource |
Accrue at: | How the costs will be allocated when monitoring the project, choice of beginning, pro rated or end. |
Base Calendar | Which of the base calendars is the resource working to |
Group | How do you wish to categorise resources by the tasks |
Code | How do you wish to categorise resources |